Construction Updates
PURPOSE
- Additional space for new District Magnet/Choice Program: Countryside Spanish Dual Immersion
- Additional space for needs of students served in Special Education
- Alignment with pre-planned construction: Parking lot reconfiguration and playground enhancement
Projected Timeline
- August 2022: Project Bids
- Fall 2022: Construction Starts - Safety fencing, excavating, footings, foundation, brick work, etc.
- Summer 2023: Bus loop, playground, parking lot work completed
- Fall 2023: Construction Complete (Exact date dependent upon multiple factors)
Communications from Karen Bergman, Principal
DROP OFF & PICK UP MAP: EXISTING VS. PROPOSED
KEY
Existing Conditions
Proposed Conditions
Project Scope
Improvements will take place in all colored regions that appear below.
BUILDING
- Spanish Immersion Program
- 6 grade-level classrooms, 2 kindergarten classrooms
- Multipurpose Room
- Centralized Special Education space
- Reconstruct existing ramp connection to be accessible, construct elevator
SITE
- Dedicated bus loop and bus entries, separated from parent drop-off traffic
- Extended parent drop-off lane, all accessed from Benton and Stuart
- Parent drop-off located at main entry
- Playground reconstruction for accessibility, in partnership with PTO
- Additional visitor parking